Suntera · Phased office fit-out · Guernsey
Completing the workplace.
Connecting the team.
The second phase at Plaza House added a client suite, further workspace and a shared café, completing Suntera’s 17,000 sq ft workplace while the first floor was already occupied.
- Client
- Suntera
- Location
- Plaza House, Guernsey
- This phase
- 5,000 sq ft
- Overall workplace
- 17,000 sq ft

01 · The brief
The next phase had
a different job to do.
With the 12,000 sq ft first floor completed and occupied, attention moved to the ground floor. This part of Plaza House would welcome clients, accommodate more of the team and provide a shared social space for people working across both floors.
POS continued from the first phase through detailed design, procurement, construction, specialist coordination and furniture installation. The task was to carry the quality and identity of the workplace through the building while giving the ground floor its own purpose.
A professional welcome
Four meeting rooms and a large boardroom, with a dedicated client arrival area.
A shared destination
A kitchen, café and breakout area for the whole business.
Additional workspace
Approximately 50 further workstation positions on the ground floor.

02 · The spaces
Privacy designed into the meeting suite.
Client rooms bring together double-glazed acoustic partitions, door specifications, wall and ceiling treatments, lighting and AV. These elements were developed as part of the room design, so the technical requirements could be coordinated before installation.
Secure access separates the public meeting suite from the operational workspace. Visitors can arrive, wait and move into a meeting room without passing through the team’s working area.
In everyday use
A clear route from arrival to meeting.
The welcome area connects directly to the meeting suite. Finishes, glazing and lighting carry the identity established upstairs into a more formal client setting, with room to wait or talk informally before a meeting.

A closer look
Two settings. One ground floor.
The client suite and café serve different needs. Each has its own atmosphere, with acoustics, lighting and furniture coordinated around how it will be used.

03 · Delivery
Delivering around
an occupied first floor.
The first-floor team was already working in Plaza House when Phase 2 began. Access, deliveries, noisy works and changes to building services therefore needed to be coordinated around an occupied workplace.
The phased approach allowed Suntera to meet its initial relocation requirements before completing the wider workplace. Maintaining continuity through the project meant the two floors could share the same design and technical standards.
The ground floor completes the workplace with client-facing rooms, further operational capacity and a shared destination for people across both floors.
04 · Project gallery
The spaces and the details.
Take a closer look at the finished project.
Select a photograph to open the full-size gallery.
The wider project
See where the project began.
Phase 1 established the 12,000 sq ft primary working floor and enabled the team’s initial move to Plaza House.